Our Projects

member name

Project :

Switch-Med Initiative (MED TEST II Project)

Client :

Egyptian National Cleaner Production Center (ENCPC)

Scope :

The project is currently implemented in 30 factories (15 in Cairo & 15 in Alexandria) by four core experts two for each Governorate. EnviGlobe works as core expert in Cairo to apply the Med-Test II principles in eight factories. The demonstrated companies with EnviGlobe are as the following:
1. Farm Frites Company at 10th of Ramadan Industrial Zone.
2. International Company for Agricultural Production and Processing ICAPP at 10th of Ramadan Industrial Zone.
3. Saudi Egyptian Company for Salts and Minerals Seco-Salt at 10th of Ramadan Industrial Zone.
4. Star Glass for Glass Manufacturing at 10th of Ramadan Industrial Zone.
5. National Company for Maize Production at 10th of Ramadan Industrial Zone.
6. Misr Café Company at 10th of Ramadan Industrial Zone.
7. Al Askary Dott Jeans for Jeans Production at Al Obour Industrial Zone.
8. Tiger Coating Company at Al Obour Industrial Zone.

member name

Project :

Implementing Energy Bench-marking in the Egyptian Ceramics Sector

Client :

Industrial Energy Efficiency Project IEE- UNIDO

Scope :

The project seeks to address some of the key barriers to industrial energy efficiency (IEE), to deliver measurable results and to make an impact on how Egyptian industries manage energy through an integrated approach that combines capacity building and technical assistance interventions at the policy and energy efficiency project level.

member name

Project :

Energy saving in the Egyptian Food Sector Phase II

Client :

Egyptian National Cleaner Production Center (ENCPC)

Scope :

The project surveyed the food sector (14 Companies) in Egypt to assess the needs of this sector for energy saving consultation. Project activities include: a survey of energy and water consumption including measurements through site visits by senior engineers and consultants to suggest recommendations for three categories of energy saving alternatives as the following:
• No Cost / Low Cost Options
• Medium Cost Options
• Investment Cost Options
Each Alternative or option supported by required calculations for the potential saving, the CO2 reduction or COD and BOD reduction, the expected investment and the payback period. All of no cost / low cost options and some of medium and investment cost options implemented during the project period, which generated success stories published by USAID.

member name

Project :

Switch-Med Initiative (MED TEST I Project)

Client :

Egyptian National Cleaner Production Center (ENCPC)

Scope :

The project scope is to transfer of Environmentally Sound Technology Program to harness the full potential of Industry contribution to Inclusive and Sustainable Development (ISID) in the South of Mediterranean Region – Egypt. the project implemented in 16 factories at hot spots areas in Alexandria Governorate. It achieved successful results and generated a lot of creative options for the demonstrated companies to save their resources in terms of raw materials, energy and water. Switchmed published success stories for Med-Test I in Egypt in its website.

member name

Project :

Design of Heat Recovery System

Client :

Ceramic Art

Scope :

Engineering design of a system to recover hot water from steam waste.

member name

Project :

Development of Training Modules for Customs Officers in E-waste management

Client :

Medical and Electronic Waste Management Project

Scope :

The project is to develop training modules aimed at raising awareness and building capacities of Customs and other relevant officers on illegal traffic of hazardous chemicals and waste under Stockholm, Basel, and Rotterdam conventions with a special focus on Electronic waste (E-waste) and Medical waste.

member name

Project :

Preparing the Environmental Register for the storage complex area

Client :

Orange Egypt

Scope :

The project aimed to prepare the required environmental registers for the storage complex area located in Aborwash industrial zone which include separate stores for electronic equipment and electronic waste, the studies include the following:
• Environmental Register for the Complex of Stores.
• Substances and Hazardous Waste Register.

member name

Project :

Preparing the Environmental Register for the three formal e-waste facilities

Client :

Sustainable Recycling Industry Project implemented by Cedare

Scope :

The project aimed to improve the recycling industry especially e-waste recycling, through preparing the required environmental registers for the formal E-waste recycling facilities which include the following:
• Three Environmental Registers for the Facilities.
• Three Substances and Hazardous Waste Register.

member name

Project :

Preparing the Master Plan of Solid Waste Management for Four Governorates

Client :

National Solid Waste Management Program NSWMP

Scope :

The general scope of the project is to prepare master plan for solid waste management in Qalyoubia, New Valley, Red Sea, South Sinai and Cairo governorates including the following:
• Assess the current situation of solid waste management in each governorate including:
- The quantities of generated waste and generation rate.
- The collection and handling methods.
- Engineering assessment for the current landfills, transfer stations and waste recycling facilities.
- Assess the current hierarchy of solid waste management in the governorate.
• Analyse the results and suggest alternatives for solid waste management, the suggested alternatives should be supported by techno-economic studies.
• Prepare short term and long term strategies for solid waste management in each governorate.

member name

Project :

Environmental Monitoring Program Management for Assiut Combined Cycle Station

Client :

Orascom for Construction

Scope :

The project aims to manage the Environmental Monitoring Program for Assiut Combined cycle station through performing the required environmental measurements every 3 months according to the program schedule and produce measurements reports that contain the measurements results and our recommendation.

member name

Project :

Environmental Impact Assessment Study for open coal handling area in Alexandria

Client :

El Fatah CO. For Trading and Supplying Services

Scope :

The project aims to prepare the required studies for obtaining the environmental license of open coal handling at El Fatah marina – Alexandria Government which include:
• Environmental impact assessment study Type (C) which include scoping session.
• Air Dispersion Modelling Study for all proposed activities in the coal handling area.
• Risk Assessment Study for all proposed activities during the construction and operation stages.
• Plant Layout Design.
• Detailed design for the handling area including all required shop drawings.
• Technical specification preparation.

member name

Project :

Engineering Supervision Services for the Rehabilitation and Upgrading of the Edwa Sorting-Composting Plant

Client :

UNDP

Scope :

The general objective of this consultancy is to provide the required monitoring of the mechanical, civil and electrical works for the rehabilitation of the Edwa Sorting-Composting Plant.
The main products of this plant will be: (i) fertilizer for agricultural activities, through the composting of organic waste, (ii) refuse derived fuel (RDF) and recyclables from the treatment of the dry fraction and, (iii) rejects to be land-filled from other fractions of MSW.

member name

Project :

Environmental Impact Assessment Study for solid waste landfill at Al Obour City, Cairo Governorate.

Client :

Cairo University/ NSWP

Scope :

The project aims to prepare the required studies for obtaining the environmental license of solid waste landfill to serve Qalyubia and Cairo Governorates at Al Obour City, Cairo Governorate which include:
• Environmental Impact Assessment Study Type (C) which include scoping session.
• Risk Assessment Study for all proposed activities during the construction and operation stages.
• Dispersion Modelling Study.

member name

Project :

Business Opportunities in the Formal Sector of Waste of Electrical Electronic Equipment WEEE Recycling

Client :

Sustainable Recycling Industry Project implemented by Cedare

Scope :

The project aims to improve the recycling industry especially e-waste recycling, through mapping of the WEEE recycling formal sector in Egypt to identify number, size, and geographic distribution of the formal industries facilities in Egypt which include several site visits for the formal facilities and interviews with the owners.

member name

Project :

Environmental Impact Assessment Study for open coal handling area.

Client :

El Salam CO. For Transport, Trading and supplying services

Scope :

The project aims to prepare the required studies for obtaining the environmental license of open coal handling at El Salam marina 2 – Alexandria Government which include:
• Environmental impact assessment study Type (C) which include scoping session.
• Air Dispersion Modelling Study for all proposed activities in the coal handling area.
• Risk Assessment Study for all proposed activities during the construction and operation stages.
• Plant Layout Design.
• Detailed design for the handling area including all required shop drawings.
• Technical specification preparation.
• Asses the company in biding and tendering process.

member name

Project :

Mapping of Informal Sector of Waste of Electrical Electronic Equipment WEEE Recycling

Client :

Sustainable Recycling Industry Project implemented by Cedare

Scope :

The project aims to improve the recycling industry especially e-waste recycling, through mapping of informal sector in the greater Cairo to identify its size and geographical distribution which include several site visits and interviews with informal collectors and recyclers over Greater Cairo areas.

member name

Project :

Environmental Studies for using coal in the industrial process

Client :

Glass Rock Company

Scope :

The project aims to prepare the required studies for obtaining the environmental license for using coal as raw material for the manufacture of rock wool at Glass Rock Factory – El Sadat City Industrial Zone – El Monofia Governorate which include:
• Environmental Impact Assessment Study Type (C) which include scoping session.
• Risk Assessment Study for all proposed activities during the construction and operation stages.
• Dispersion Modelling Study for the expected air emissions

member name

Project :

Engineering Supervision for the Solid Waste Management Offices Renovation at Four Sites

Client :

GIZ

Scope :

The general objective of this consultancy was to provide the required monitoring of the mechanical, civil and electrical works for the rehabilitation of the SWM offices located at:
• Matareya – Cairo Governorate.
• Khosous – Qalyoubia Governorate.
• Shoubra El Khema – Qalyoubia Governorate.
• Qalyoub – Qalyoubia Governorate.

member name

Project :

Environmental Impact Assessment Study for open coal handling area.

Client :

The National River Ports Management Company

Scope :

The project aims to prepare the required studies for obtaining the environmental license of coal handling at El Watanya store – El Nubaria Canal- Alex Government which include:
• Environmental Impact Assessment Study Type (C) which include scoping session.
• Risk Assessment Study for all proposed activities during the construction and operation stages.
• Plant Layout Design.
• Detailed design for the handling area including all required shop drawings.
• Technical specification preparation.
• Asses the company in biding and tendering process.

member name

Project :

Environmental Impact Assessment Study for open coal handling area

Client :

The National River Ports Management Company

Scope :

The project aims to prepare the required studies for obtaining the environmental license of coal handling at El-Nor El Din Marine – El Nubaria Canal - Alexandria Governorate which include:
• Environmental Impact Assessment Study Type (C) which include scoping session.
• Risk Assessment Study for all proposed activities during the construction and operation stages.
• Dispersion Modeling Study for the expected air emissions
• Plant Layout Design.
• Detailed design for the handling area including all required shop drawings.

member name

Project :

Rehabilitation and Upgrading of the Edwa Sorting-Composting Plant

Client :

Minya Solid Waste Management Project

Scope :

Implementation of a pilot solid waste management project aiming at strengthening the current technical, financial and organizational structure of the current waste management system in Minya, through modernizing and developing the overall waste management and recycling system with the Italian experience.
The general objective of this consultancy was to provide the following:
• Review; discuss the appropriateness and adequacy of a schematic design set by an international consultant for a recycling facility – Compost and RDF.
• Prepare the final design document including the final schematic design, Process flow, technical requirement specifications, BoQ based on best allocation of budget elements.
• Prepare the tender documents according to UNDP specifications and using FIDIC guidelines and standards.
• Manage the process of bidding and post bidding evaluations, placement and contracting based on best value for money (BVFM).

member name

Project :

Site Characterization for Taba Station.

Client :

EXXON Mobil

Scope :

The project aims to perform site characterization phase I for the Exxon Mobil petroleum filling stations at Taba Heights Station in South Sinai Governorate to assess the environmental statues of the underground water and soil for the site.

member name

Project :

Engineering Supervision Services for the Construction of Solid Waste Transfer Station

Client :

GIZ

Scope :

Engineering Supervision Services for the Construction of the Integrated Resource and Recovery Center (Solid Waste Management) and Solid Waste Transfer Station. The general objective of this consultancy was to provide the required monitoring of the mechanical, civil and electrical works of both the IRRC and Transfer station projects in El- Khanka and Khosoos cities respectively.

member name

Project :

Nile Jetty at El Tabeen (Transfer Station for coal handling)

Client :

El Salam CO. For Transport, Trading and supplying services

Scope :

The project aims to prepare full detailed design of coal discharge transfer station to transport by road trucks including required steel structure design and hopper according to the environmental legislation requirements. This shall be part of full EIA study for the location.

member name

Project :

Environmental Impact Assessment Study for open coal handling area.

Client :

El Salam CO. For Transport, Trading and supplying services

Scope :

The project aims to prepare the required studies for obtaining the environmental license of open coal handling at El Salam marina – El Nubaria Canal - Alexandria Governorate which include:
• Environmental Impact Assessment Study Type (C) which include scoping session.
• Air Dispersion Modelling Study for all proposed activities in the coal handling area.
• Risk Assessment Study for all proposed activities during the construction and operation stages.
• Plant Layout Design.
• Detailed design for the handling area including all required shop drawings.
• Technical specification preparation.
• Asses the company in biding and tendering process.

member name

Project :

Environmental Impact Assessment Study for open coal store.

Client :

El Salam CO. For Transport, Trading and supplying services

Scope :

The project aims to prepare the required studies for obtaining the environmental license of open coal store at El Salam storage area, Arab Abo Saad, Helwan, Cairo Governorate which include:
• Environmental Impact Assessment Study Type (C) which include scoping session.
• Air Dispersion Modelling Study for all proposed activities in the coal handling area.
• Risk Assessment Study for all proposed activities during the construction and operation stages.
• Plant Layout Design.
• Detailed design for the handling area including all required shop drawings.
• Technical specification preparation.
• Asses the company in biding and tendering process.

member name

Project :

Engineering Supervision Services for the Rehabilitation of the Old Line for the RDF, Compost and Recyclables Recovery

Client :

GIZ

Scope :

The general objective of this consultancy was to provide the required monitoring of the mechanical, civil and electrical works of the rehabilitation of the old line for the RDF, compost and recyclables recovery – Elkhanka, Qalyoubia governorate.

member name

Project :

Installation of four new units for Salt Production.

Client :

EMISAL

Scope :

The project aims to prepare the Environmental Studies required by EPAP III “Funding Project” which includes:
• Feasibility study
• Environmental Audit
• Compliance Action Plan
The Installing of the four new units will modify the current environmental status by using the residual bittern as the raw material for extracting (Bromine, potassium sulphate, magnesium chloride and boron salts).

member name

Project :

Belbis Land Development

Client :

Egyptian National Cleaner Production Center (ENCPC)

Scope :

The project aims to develop 720 acres at Belbis area in El Sharqia Governorate. The suggested development includes movement of charcoal pits which spreads on the residential and agricultural areas.

member name

Project :

Environmental Impact Assessment Study for coal discharging and handling.

Client :

The National River Ports Management Company

Scope :

Environmental Impact Assessment Study for coal discharging from ships on barges and/or trucks at Alexandria Port - Under supervision of Alexandria Governorate.

member name

Project :

Compliance Action Plan

Client :

EFACO

Scope :

The project aims to prepare Compliance Action Plan for coal handling in the factory which is used in the manufacture of ferro silicon alloys.

member name

Project :

Environmental Impact Assessment Study for coal handling.

Client :

National Nile Company for River Transportation.

Scope :

The project aims to prepare the required studies for obtaining the environmental license of open coal handling at El Salam marina – El Nubaria Canal - Alexandria Governorate which include:
• Environmental impact assessment study Type (C) which include scoping session.
• Air Dispersion Modelling Study for all proposed activities in the coal handling area.
• Risk Assessment Study for all proposed activities during the construction and operation stages.
• Plant Layout Design.
• Detailed design for the handling area including all required shop drawings.
• Technical specification preparation.
• Asses the company in biding and tendering process.

member name

Project :

Engineering Consultancies for NSWMP funded by the GIZ in cooperation with the Ministry of Environment

Client :

GIZ / NSWMP

Scope :

The general objective of this consultancy was to provide engineering consultancy to check and review the specs. of the new equipment of solid waste management (SWM) which was procured by NSWMP for the SWM models in four governorates.

member name

Project :

Environmental Impact Assessment Study for coal discharging.

Client :

El Salam CO. For Transport, Trading and supplying services

Scope :

The project aims to prepare Environmental Impact Assessment Study for discharging from ships on barges and/or trucks at Alex port – Alexandria Governorate.

member name

Project :

Compliance Action Plan for Tahrir Station.

Client :

EXXON Mobil

Scope :

The project aims to prepare Compliance Action Plan study required by EEAA.

member name

Project :

Establishing a Formal Lead Smelter using Lead Acid Batteries (El Masreya for Smelting, Refining and Manufacturing of Lead)

Client :

USAID- CAIP Project

Scope :

The general objective of this consultancy was to transfer the informal lead smelting facility to formal facility through the following:
• Developing the facility layout
• Identifying the state of the art equipment
• Designing the pollution control equipment.
• Preparing Environmental Social Impact Assessment ESIA
• Developing the technical specs of equipment.
• Managing the purchasing and installation of equipment.

member name

Project :

Site Characterization of four sites

Client :

EXXON Mobil

Scope :

The project aims to perform site characterization for the Exxon Mobil petroleum filling stations to assess the environmental statues of the underground water and soil for the site. The sites location are 10th of Ramadan Depot, Belbis Station, ElSudan street station and Mahalla1 and Mahalla 2 stations.

member name

Project :

Fuel switching from Mazot to Natural Gas

Client :

Edfu Sugar Factory

Scope :

Environmental Audit, Compliance Action Plan and Environmental Impact Assessment. The project was financed by the KFW.

member name

Project :

Environmental Studies and Engineering Supervision for the Installation of an IWWTP

Client :

Pachin Factory in Alexandria

Scope :

• Feasibility Study (Environmental Audit); the study entailed the design and specifications of the plant including civil and electro-mechanical work
• Compliance Action Plan
• EIA study (Form B)
• Supervision for the installation of the IWWTP
(The general objective of this supervision is to provide the required monitoring of the mechanical, civil and electrical works of the plant)

member name

Project :

Site Characterization of 43 Shell Filling Stations

Client :

Shell Marketing

Scope :

Site Characterization including:
• Workplace air quality
• Industrial Waste Water Quality
• Underground soil characterization
• Underground water characterization

member name

Project :

Site Characterization of Filling Station and Hazardous Waste Management

Client :

EXXON Mobil

Scope :

Site Characterization and Clean-up Plan in Alexandria site.

member name

Project :

Shallow Underground Water Identification

Client :

EXXON Mobil

Scope :

Shallow Underground Water Identification of 51 Filling Station all over Egypt.

member name

Project :

Preliminary Assessment of Petrol Station

Client :

EXXON Mobil

Scope :

Phase I assessment (URM) of El Ain El Sokhna Mobil Station.

member name

Project :

Compliance Action Plan – EIA for New Activities

Client :

Electrolux Company (Olympic Group) – Water Heaters Factory

Scope :

• Preparation of Compliance Action Plan for the whole factory and Implementing the compliance actions needed to reach compliance (installation of Industrial Waste Water Treatment Plant - IWWTP)
• Preparing an EIA for the factory new activities
• The service design and preparation of the technical specifications and tender documents for two IWWTP.
• Supervision of supply and installation of civil work, mechanical and electrical equipment

member name

Project :

Preparation of Environmental Studies needed for the Installation of an IWWTP

Client :

Electrolux Company (Olympic Group) – Water Heaters Factory

Scope :

• Preparation of documents needed for the installation of an IWWTP (Industrial Wastewater treatment plant).
• Preparation of an EIA for the plant.

member name

Project :

Hazardous Waste Management Project

Client :

El Masreya for Smelting, Refining and Manufacturing of Lead

Scope :

• Facility design to accommodate machineries to produce 1 million lead batteries per year fabricated from lead resulting from recycled used batteries (Hazardous Waste).
• Specifying the required civil work for the project.
• Specifying the required machinery including electro-mechanical equipment.
• EIA study (type C) including a socio-economic study and public hearing

member name

Project :

Design and Preparation of the technical specifications

Client :

Delta Steel Company, Shoubra El Kheima, Egypt

Scope :

Engineering design and preparation of technical specifications of the primary and secondary pollution control systems for two 25 ton capacity arc furnaces.

member name

Project :

Environmental Studies for Installation of new production Unit

Client :

Al Arabeya for Medical Industries Company (MEDIC), Sadat Industrial City, Egypt

Scope :

Environmental Audit, Compliance Action Plan and Environmental Impact Assessment. The project was financed by the KFW.

member name

Project :

New Washing Machine Factory EIA

Client :

Universal Group, Six of October Industrial City, Egypt

Scope :

Environmental Impact Assessment Study for the new factory and the Industrial Waste Water Treatment Plant (IWWTP)

member name

Project :

Gas Cookers Factory Studies

Client :

Universal Group, Six of October Industrial City, Egypt

Scope :

Environmental Audit, Compliance Action Plan, Specifying the required equipment and the EIA for the (IWWTP). The Project was financed by The Egyptian Pollution Abatement Project Phase II (EPAPII)

member name

Project :

Updating of Environmental Register

Client :

ARMA Group

Scope :

Updating of the Environmental Register for the whole Factories that belong to the Group.

member name

Project :

Environmental Impact Assessment (EIA)

Client :

ARMA Group

Scope :

Environmental Impact Assessment for the Margarine Production Plant

member name

Project :

Fuel switching from Mazot to Natural Gas

Client :

Six of Mahmoudia, Behera Governorate Brick Factories, Egypt

Scope :

Environmental Audit, Compliance Action Plan and Environmental Impact Assessment. The project was financed by the KFW.

member name

Project :

Fuel switching from Mazot to Natural Gas

Client :

Five of Banisuef Governorate Brick Factories

Scope :

Environmental Audit, Compliance Action Plan and Environmental Impact Assessment. The project was financed by the KFW

member name

Project :

Environmental Studies

Client :

Arab Pharmaceutical Glass Co.

Scope :

The project includes preparing the environmental studies “Environmental Impact Assessment, Compliance Action Plan and Environmental Register” required by EEAA to comply their environmental status.

member name

Project :

Environmental Studies for new extension

Client :

El Helal and Golden Star

Scope :

The project includes preparing the environmental studies “Environmental Feasibility Study, Compliance Action Plan and Environmental Impact Assessment” required by EEAA to implement new modifications in three factories which aims to make the factories compliance with environmental regulations. The project was financed by the KFW.

member name

Project :

Fuel switching from Mazot to Natural Gas

Client :

Six of Kafr El Sheikh Brick Factories

Scope :

Environmental Audit, Compliance Action Plan and Environmental Impact Assessment. The project was financed by the KFW.

member name

Project :

Textile Factory EIA (Two Factories)

Client :

Zenotex Company

Scope :

Environmental Impact Assessment Studies for two new factories

member name

Project :

Development of the Existing Design of Tanning System (Tanning Drum and Driving System)

Client :

Tanning Industry, Egypt

Scope :

Engineering design and development of 3 m diameter tanning drum including: driving system, control, gear drive, and accessories.

member name

Project :

Preparation of an Environmental Impact Assessment (Type C), Feasibility Study, and a Compliance action plan.

Client :

The Egyptian Mineral and Salt Company

Scope :

The project is based in Faiyum, and the company is comprised of three factories, one deal with vacuum salts, the other pharmaceuticals, and lastly one deal with packaging of these products. The scope involved preforming the three studies to ensure that all industrial activities comply with environmental regulations.

member name

Project :

Storage Facility EIA

Client :

Engineering Company for Containers

Scope :

Environmental Impact Assessment Study

member name

Project :

General Storage Facility EIA

Client :

Engineering Company for Containers

Scope :

Environmental Impact Assessment Study

member name

Project :

Preliminary Risk Assessment for Land Contamination

Client :

Lilly Egypt, Six of October Industrial City, Egypt

Scope :

Land Contamination Assessment